Implementation of the e-Invoice Solution – mib:Peppol

How the Project Runs and What to Prepare For

Article author: Marián Mráz (Head of Project Delivery)

arrow_back Back to news

From 1 January 2027 electronic invoicing will become the standard way of exchanging invoices for domestic transactions in Slovakia that are subject to the statutory obligation. However, it is not just about creating an XML file. A company must prepare its processes, data, ERP system, connection to the Peppol network and the way errors are handled.

The good news is that implementing e-Invoicing does not have to mean a major disruption to the accounting team’s day-to-day work. With a properly set up project, you can proceed systematically, with clear decision points and sufficient time for testing.

The project starts with technical and process preparation

The first step is not installing the solution but verifying readiness. The project scope, schedule, project team and responsibilities for IT, finance, security and archiving need to be confirmed with the customer. From the technical point of view, you need to verify the ERP system version, the availability of development, testing and production environments, and the way of connecting to the integration layer.

Equally important is the process analysis. The company must define which documents it issues and receives and how it handles credit notes, advance invoices, attachments or manually created FI documents. In an SAP environment, existing customer-specific modifications, for example in SD billing, also need to be reviewed.

Part of the preparation is also a master data check. Based on the issues identified, the customer corrects or completes partner identification data, addresses and bank accounts, for example.

Data mapping, configuration and testing follow

Already during the analysis, the basic installation and setup of mib:Peppol is carried out as part of the Quick Start. Sending and receiving the first test document verifies that the connection works. In parallel, based on the process and data analysis, the target solution concept (Business Blueprint) is prepared, which the customer approves and which serves as the basis for configuration and data mapping.

An electronic invoice is a structured XML document that the accounting system must be able to process automatically. That is why the core of the project is precisely the correct mapping of data from the ERP: supplier and customer identification, VAT identification number, addresses, line items, taxes, payment details, units of measure, references to original documents and attachments.

After the solution and the integration connection are configured, end-to-end testing follows. The entire flow is verified: from creating the invoice in the ERP through XML transformation and validation, transmission of the invoice over the Peppol network and sending tax data in the TDD format to the Financial Administration of the Slovak Republic to processing technical statuses and delivery receipts and retaining the related documents.

You need to test representative scenarios, not just one “ideal” invoice. Tests should also include credit notes, advance payments, attachments, missing data, rejected documents and reprocessing after an error has been corrected.

Go-live needs a clear operating model

Preparation for live operation also includes training the IT team and key users.

Before go-live, the following must be in place: a cutover plan (a plan for the transition to live operation), monitoring, access authorisations, escalation contacts and an incident handling procedure. Accountants should know where they can see the status of a document and how to proceed in case of an error. The IT team, in turn, needs technical logs, monitoring and clearly defined support.

After go-live comes a period of enhanced support (hypercare). Transmissions are monitored, incidents are resolved and operations are stabilised. The solution is then handed over to standard support.

Practical experience from pilot projects shows that the biggest risk is not the installation itself. The risk is usually a project scope confirmed too late, incomplete master data, an unverified integration connection or too little time for testing.

The duration of the project depends mainly on the availability of system access and test data, the readiness of master data, the number of companies and scenarios involved, existing modifications and the scope of integration or customer extensions.

Start early: Prepare a technical review, a list of invoicing scenarios and samples of real documents. This allows sufficient time for thorough testing before January 2027.

Find out whether your SAP or other ERP system is ready for e-Invoicing. Download the readiness checklist.

Start with Peppol e-invoicing

Schedule a free consultation. We will help you choose the right implementation path and provide a detailed cost estimate.

What you get

  • Full readiness for Slovak eFaktúra legislation
  • Automated reporting to the Financial Administration of Slovakia
  • Document status tracking throughout the entire transfer
  • Secure processing according to Peppol PKI standards